Watermark.
Bowling Green · Middleton Twp
Switch site 38 sites · 11 basins 8 open

Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Live

Power & ratepayers

Whose grid this load lands on, and what it does to the households on the same wires.

Partial
  • the campus load is a screening bracket — the demand-pressure read is withheld until an instrument grounds it

Every megawatt figure about a data center sits over a denominator, and that denominator is somebody's grid. A real impact study names the grid and cites the source. It then states what the campus load does to the households on the same wires.

Whose grid this is

Link Identification Evidence
Serving retail utility City of Bowling Green - (OH) [reference]
Holding company City of Bowling Green - (OH) [reference]
Balancing authority PJM Interconnection [reference]
Wholesale market (RTO/ISO) PJM Interconnection (RTO/ISO) [reference]
Retail rate regulator municipal (home rule, OH) [reference]

What those systems already carry

System Annual load Campus share
City of Bowling Green - (OH) 518 GWh/yr 362.86%
PJM Interconnection 815,056 GWh/yr 0.23%
State retail sales 161,934 GWh/yr 1.16%

The disclosed campus draws ~239 MW — at a 0.9 load factor, ~1,880 GWh/yr, the numerator of every share above. The draw is itself an [inference].

The campus against consumer prices

The demand → consumer-price read needs an instrument-grounded campus load — an air permit or a filed disclosure. This site's load is a screening bracket, so the read is withheld rather than computed off an inference — the gap panel below names the instrument that would ground it.

  • Grid foundation layer (#94). The state, City of Bowling Green - (OH), and PJM denominators are now all connector-sourced — Ohio retail from EIA (shared with #91), per-utility retail from the EIA-861 file, and PJM annual demand from EIA-930. The campus is a single load equal to a material fraction of its serving utility's entire retail sales. Denominator vintages differ (utility EIA-861 2024 / BA EIA-930 2024 / state EIA 2025 (1-year spread)): the EIA state seriesid route publishes ahead of the EIA-861 bulk file and the EIA-930 annual sum, so the three shares are not struck against one common year.

The cited service chain with its full citations, the cohort-price qualification, and the load report's inference chain are in the grid annex.

Reading this chapter · Bowling Green · Middleton Twp · updated 2026-08-05

This campus does not draw its power from the grid. It is designed to be fed behind the meter by the Apollo Power Generation Facility350 MW net of gas generation plus a 119.5 MW / 239 MWh battery, twenty-one turbines and six reciprocating engines, capable of 491 MW gross at design conditions before derate. [verified]

It was certified on 2026-02-03 by automatic approval, with no public hearings, under Ohio’s accelerated Letter of Notification track — case 25-0973-EL-BLN.

The suffix is the story

BLN is a Board Letter of Notification: the accelerated route that produces an automatic approval and holds no adjudicatory hearing. BGN is the adjudicated generation-certificate track — a proceeding that did not happen here. The Power Siting Board’s own press release prints the wrong suffix, and drops a leading zero besides. The docket caption, all twenty-two Staff Report page footers, and the electronic filing stamp all say BLN. [verified]

A case number is a claim about what kind of proceeding occurred. Getting it wrong does not merely misfile the document — it asserts a hearing that never took place.

Read the conditions, not the headline

Condition 15 bars any physical or electrical interconnection with the PJM Transmission Systemrec ; Condition 16 requires a PJM new-service request and supplemental Board approval before any export; Condition 14 caps output at 350 MW net. [verified]

That is why the modelled grid draw is about zero — and why the plant appears nowhere in EIA-860M, the federal generator inventory, in any state, on any sheet. Two readings, neither asserted here: a plant its certificate bars from the transmission system may be outside Form 860’s scope, or this may be reporting lag. If the first holds, the behind-the-meter pathway makes large generation statistically invisible to the inventory every fleet-level count runs off. [open]

Meta’s own letter to the township trustees says that “through our partnership with First Energy, Meta will pay for millions of dollars in new energy infrastructure investments — network upgrades, utility substations, and transmission lines.” [reference] A behind-the-meter campus paying for transmission is not a contradiction, but it is the largest open question on the power side, and this study holds it open rather than resolving it.

The Staff Report is captured. The application, the ODNR review letter, the data-request responses, the public comments and the Board’s own approval entry are not: the docketing system serves a JavaScript bot challenge to automated retrieval, and the Ohio Secretary of State returns HTTP 403. An access failure is a fact about a server, never about a record — recorded with its date and its response code, and nothing inferred from it.

The record behind this chapter

What this chapter stands on: the records it reads, the inputs its modeled figures rest on, and the reference data behind its baselines — the same pages the record screens serve, not a second copy. A figure the record does not support stays [open] and links nothing.

Reference data