Watermark.
Lima BOSC
Switch site 38 sites · 11 basins 8 open

Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Building
The record
Record · Enforcement

correspondence

edoc-3170394
[verified]
Fields
agency
City of Lima, Ohio / Ohio EPA Division of Surface Water
instrument
correspondence
case_no
respondent
City of Lima, Ohio
facility
Lima Wastewater Treatment Plant (Lima WWTP)
permit_no
2PE00000
issued_date
2015
effective_date
supersedes
penalty_usd
stipulated_penalties
status
summary
This is a status-report letter from Russell C. Bales, Supervisor of the City of Lima WWTP, to Ms. Peggy Christie at the Ohio EPA Division of Surface Water Northwest District Office. It reports on the construction contracts for the Headworks and Primary Clarification Improvements at Lima WWTP, noting that the guaranteed maximum price has been established, bids are divided into 7 major packages, and notice to proceed is anticipated by June 15, 2015. Peterson Construction Company/URS (now AECOM) are the Construction Managers at Risk (CMAR).
note
obligations
    • requirement CMAR (Peterson Construction Company/URS) to submit bids for any work they intend to self-perform to the City of Lima
    • deadline 2015-06-02T15:00:00
    • status
    • requirement All other subcontractors to e-mail bids to Mike Fritchie with Peterson Construction Company/URS
    • deadline 2015-06-03T10:00:00
    • status
    • requirement Notice to proceed with Headworks and Primary Clarification Improvements project anticipated
    • deadline 2015-06-15
    • status
⚠ Gaps in the record
  • Exact issued date not printed on the letter — no explicit date visible in the letter body or header; estimated from context as sometime before June 2, 2015.
  • Permit number '2PE00000' read from handwritten notation at top right of page; OCR rendered it as 'b0000' and image shows '2PE00000' — verified against image.
  • This is a status-report correspondence letter, not a formal enforcement instrument (consent decree, DFFO, NOV, etc.); it is filed under a permit/case but does not itself impose orders or penalties.