Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Live

The gap inventory

Every gap this study names, with the record that would close it and where to send it.

On the record

This page collects every ask the study makes: 6 gaps named across 6 chapters. Each ask names a public record that an office could produce tomorrow. Each is the same ask the site's leads board already tracks, never a second copy of it. An absence on this page is a finding, not a locked door.

What this study cannot compute yet

A real impact study would report how much heat the discharge adds to a reach screened against Ohio's numeric temperature criterion at its design low flows. [open]

Computing it requires a thermal characterization for this project — none exists on the record.

A real impact study would report the wells within the drawdown radius, and whether construction dewatering was permitted and where the water went. [open]

Computing it requires a well survey and any dewatering record — neither has been produced.

A real impact study would report the dispersion footprint of the campus's permitted backup-generator fleet. [open]

Computing it requires an air-permit application for this project — none is on the record.

A real impact study would report the campus's share of the serving utility's, balancing authority's, and state's annual load, from a grounded load figure. [open]

Computing it requires an instrument that grounds the IT load — an air permit or an interconnection filing; the load on the record is a screening bracket.

A real impact study would report what tax revenue is being traded away and for how long, before the trade is approved. [open]

Computing it requires the county auditor's abatement report and the year-by-year exemption ledger — public records, none produced into this record. Where the agreement itself is on the record it states the TERMS of the trade, never its cost to the taxing bodies.

The site's open questions beyond these chapters

  • [open] Three different fill volumes, two incompatible framings, and no instrument behind any of them data/extracted/van-wert/incentive-water-instruments.yaml · data/extracted/van-wert/mega-site-instruments.yaml · data/reference/oepa/cooling-reconciliation.yaml
  • [open] The operator's FAQ names the one document that would settle campus water capacity data/documents/van-wert/operator/2026-08-05-qts-van-wert-project-faq.q-com.html · data/extracted/van-wert/incentive-water-instruments.md
  • [open] The runway was laid across 2014-2016, and none of the three agreements that laid it is in the corpus data/extracted/van-wert/mega-site-instruments.yaml · data/documents/van-wert/council/26-05-028.pdf
  • [open] No signed or certified copy of any of the six ordinances is public data/extracted/van-wert/mega-site-instruments.yaml · data/documents/van-wert/council/26-05-028.pdf
  • [open] The hearing notice names four parcels; the assemblage has five data/extracted/van-wert/mega-site-instruments.yaml · data/reference/van-wert/parcel-assemblage.geojson
  • [open] 1.1 acres between the zoned area and the deeded holding, unattributed data/extracted/van-wert/bosc-site-footprint.yaml · data/extracted/van-wert/mega-site-instruments.yaml
  • [open] The Marsh Foundation → Thor → QTS deed chain is not closable from the parcel layer data/reference/van-wert/parcel-assemblage.geojson · data/extracted/van-wert/bosc-site-footprint.yaml
  • [open] The air permit-to-install is a dated instrument-grade negative, and it is what would move the facility domain data/extracted/oepa/van-wert/2GC08872.noi.npdes.yaml · data/extracted/van-wert/regulatory-watch.yaml
  • [open] The *WD modification's first CSO construction milestone came due 2026-08-01 and is untested data/extracted/van-wert/water-watch.yaml · data/extracted/van-wert/regulatory-watch.yaml
  • [open] The instrument holding the CSO overflow total is the same one that is not being filed data/extracted/van-wert/water-watch.yaml
  • [open] No co-permittee NOI has been filed, so the general contractor is unnamed data/extracted/oepa/van-wert/2GC08872.approval.npdes.yaml
  • [open] A nationwide-permit verification is never public-noticed, so silence here can never become absence data/extracted/oepa/van-wert/2GC08872.noi.npdes.yaml
  • [open] No document in the corpus states this campus's MW, including the transmission case named for it data/extracted/grid/van-wert/van-wert-haviland-138kv.project.yaml · data/extracted/van-wert/mega-site-instruments.yaml
  • [open] An incentive package exists as a negotiation and as no instrument data/extracted/van-wert/incentive-water-instruments.yaml · data/documents/van-wert/council/7.13.26.pdf
  • [open] The state data-center sales-tax exemption is paused, and this project has never requested one data/extracted/van-wert/incentive-water-instruments.yaml
  • [open] The local ballot route against the zoning is closed, and it was an initiative rather than a referendum data/extracted/van-wert/regulatory-watch.yaml
  • [open] Ordinance 26-06-034 does not do what Council moved to do data/extracted/van-wert/incentive-water-instruments.yaml · data/documents/van-wert/council/26-06-034-DRAFT.pdf

The full board, with lifecycle and filters, is at open leads and open questions.

Sections of the site still awaiting a source

Distinct from the study's gaps: these are whole sections of the record that have not opened yet — the needs board's asks, not the study's.